RAPID PACKAGE 3 AREA 1, PENGERANG
Client : Zhonghe Huaxing Development (M) Sdn Bhd
Project: Contract of Installation of Precast Columns and Beams for RAPID 3 Project
Structural System :
Precast Columns (200 nos) and Precast Beams (1405 nos)
Scope of works: Installation and Launching Precast Concrete Piperack.
Completion Period: 6 months (April 2016 – September 2016)