Q-Cell Solar Cell Factory, Cyberjaya

Q-Cell Solar Cell Factory, Cyberjaya

Client : M+W Zander

Project: 3 blocks of 2-3 storey buildings ( FAB, CUP & SPINE), Floor area 30,000m²

Structural System:
Precast Columns, Precast Beams, Precast Double Tee slab, Precast Hollow Core Slab, Precast Planks and Façade Walls

Our scope of works:
Design, manufacture and installation of precast components, grouting of joints, beam top concrete and related works. Site planning and management of the above works.

Completion Period: 6 months (July 2008 – March 2009)